U Center 2 in Bucharest

Workplace charging deployed in phases across a multi-tenant office building - with parking-level caps, BMS-integrated allocation, and tenant reporting built in.

56 stations and 1.232 kW deployed in phases - zero outages, no grid upgrades.

56

Charging stations

1.232 kW

Installed capacity

Bucharest

Romania

U Center 2 building exterior - Bucharest

OPERATIONAL RESULTS

~10 MWh

Avg. monthly energy for charging

~700

Charging sessions per month

Up to 45

Peak simultaneous sessions

Zero

Outages reported

“At U Center 2, we needed workplace charging that could scale without exceeding strict electrical limits. Voltic’s local control and BMS-based allocation keep charging predictable during peak demand, with clear tenant-level reporting and minimal operational overhead.”

Forte Partners

Victor Motatu

MEP Development Manager, Forte Partners

FULL CASE STUDY

Get the complete story

The full case study covers every technical detail of this deployment - from challenge to results.

Multi-level load management architecture
BMS-integrated dynamic power allocation
Tenant grouping and billing workflows
Full operational results and signals