Workplace charging deployed in phases across a multi-tenant office building - with parking-level caps, BMS-integrated allocation, and tenant reporting built in.
56 stations and 1.232 kW deployed in phases - zero outages, no grid upgrades.
56
Charging stations
1.232 kW
Installed capacity
Bucharest
Romania

OPERATIONAL RESULTS
~10 MWh
Avg. monthly energy for charging
~700
Charging sessions per month
Up to 45
Peak simultaneous sessions
Zero
Outages reported
“At U Center 2, we needed workplace charging that could scale without exceeding strict electrical limits. Voltic’s local control and BMS-based allocation keep charging predictable during peak demand, with clear tenant-level reporting and minimal operational overhead.”
Victor Motatu
MEP Development Manager, Forte Partners
FULL CASE STUDY
The full case study covers every technical detail of this deployment - from challenge to results.